Year: 2013-2014
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Construction of a new quay wall for the extension of Port of Fujairah Oil Terminal 2, Phase 2, Berths 8 and 9. The total length of the quay wall is 890m and has a retaining height of 23.6m. The structure is a combi wall with driven Ø1420mm tubular piles. As anchoring system MV piles were used with a total length of 50m. The structure has been installed using marine equipment.
MUC Engineering: Client’s Consultant for detailed design and Project Management and Supervision.