Year: 2013
Location: Fujairah – UAE
Description: Development of New Fisherman Harbour including quay walls, breakwaters and dredged basin. The total length of the quays is approx. 900m.
MUC Engineering: Contractor Consultant for detailed design and numerical modeling studies.
Category: Coastal and River
Emirates LNG Reclamation Project
Year: 2013
Client: Government of Fujairah, Fujairah Municipality
Location: Fujairah – UAE
Description: Reclamation of land and coastal protection for development of LNG terminal in Fujairah.
MUC Engineering: Client’s Consultant for detailed design, tender document preparation and project supervision.
Port of Fujairah Northern Breakwater
Year: 2013-2015
Client: Port of Fujairah / Government of Fujairah
Location: Fujairah – UAE
Description: Port of Fujairah Northern Breakwater Project for enclosing of OT2 harbour basin. The total length of the breakwater is 3km. It extends into deep water to a depth of 26m.
MUC Engineering: Client’s Consultant for modeling, detailed design and Project Management and Supervision.
Al Sadr Port Extension
Year: 2012 (completed)
Location: Abu Dhabi – UAE
Description: Development of Al Sadr Port Extension, including quay walls construction, coastal protection works, reclamation and dredged a basin to CD-6m. The total length of the quay walls is 1,100m, these are steel sheet piles anchored with a tie back anchors to a steel sheet pile anchor wall.
MUC Engineering: Contractor Consultant for detailed design and numerical modeling studies.
Coastal protection Port of Fujairah
Year: 2009
Location: Fujairah – UAE
Client: Port of Fujairah
Description: Hydraulic design including wave penetration study, guidance of the tender process and supervision over 1 km of breakwater.
Fujairah Northern Land Reclamation Project
Year: 2009-2011 (completed)
Client: Government of Fujairah, Fujairah Municipality
Description: Fujairah Northern Land Reclamation Project Phase 1, Reclamation of 225 hectare of new land including 5.8km of coastal protection. The reclamation fill material was rock, obtained from a nearby quarry. A total of 56 million ton has been produced to create the new land.
MUC Engineering: Client’s Consultant for detailed design, modeling studies Supervision and Project Management.
Revetment Fujairah Northern Land Reclamation Project
Year: 2008-2011
Location: Fujairah – UAE
Client: Government of Fujairah
Description: Design guidance of tender process of 5 km revetment.
Port of Fujairah, OT2 Phase 1
Year: 2008-2010 (completed)
Client: Port of Fujairah
Location: Fujairah – UAE
Description: Realization of a quay wall for Port of Fujairah Oil Terminal 2, Phase 1 Including construction of 1.5km of combi wall with a retaining height of 22.8m, 800m of deep water breakwater and 5 million m3 of dredging and reclamation. After completion the facility is able to receive 4 tankers up to a size of 200,000 DWT or 8 handy size tankers.
MUC Engineering: Client’s Consultant for detailed design, Supervision and Project Management.